1. Inspect for compliance with best management practices
  2. Construction exits and entrances

    •  Install according to approved plan, if shown.
    •  Use 1.5″-3.” stone.
    •  Minimum pad width of 20 feet.
    •  Minimum pad length of 50 feet.
    •  Excavate footpring 3 inches.
    •  If tire washing is required, route runoff from washing to an approved
      sediment trap or sediment basin.
    •  Install filter fabric under the entire pad.
  3. Inspect discharge points and downstream off-site areas for impact.

  4. Walk the perimeter of the site.
  5. Inspect active areas.
  6. Inspect disturbed areas that are not currently being worked.
  7. Inspect disturbed areas with final stabilization.
  8. Take into account the overall site.